Spearheaded research and implementation of the Last Planner System (LPS) with MS Project and Power BI analytics.

Traditional scheduling suffers from cascading delays; controls lacked a way to measure workflow reliability.
Spearheaded research and implementation of the Last Planner System (LPS) with MS Project and Power BI analytics.
Enhanced schedule predictability and introduced Percent Plan Complete (PPC) to drive continuous improvement.
As co-author in Waskita's R&I Department, I bridged Lean Construction theory with practical scheduling (Doc WSKT-CO-ENG-B-RP-0010-R0).












Introduced PPC to measure reliability with weekly tracking.
Lookahead windows from MS Project baselines to remove constraints.
Reasons for Non-Complete (RNC) tracking to resolve impediments.
Documentation reviewed by senior leadership including Prof. Ir. M. Agung Wibowo, Ph.D.
MS Project schedules with Power BI control boards (Beckayu 2A Ujung).
Protocols aligning superintendents, subcontractors, and planners.